When the planning for this project first started, I looked at options for power and heat. We have natural gas so I though maybe we could have Ameren run another gas and electric line to the shop. However the distance from the current service and the fact that they would have to lay the gas line over or through the septic system made option 1 a no-go.
I really did not want an LP tank sitting in the yard, even if I could hide it in the landscaping. Option 2 was also a non-starter.
Option 3 would be the plan. I would use electric heat for the workshop. It would a little more expensive to heat the building using electric but the upfront costs would be much lower plus the plan was doable.
With the electrical service, I had caught a break. A previous owner at one time, had a hot tub sitting outside at the south-west corner of the house-the closest point to the new workshop. It had been hardwired to the service box some 100′ away. After opening up the box and testing the breaker, I found that it was wired for 220 volts with #4 aluminum wire. At the other end was a 50 amp breaker. That would not be enough amperage to run the garage but after some research, I found that I could run up to 80-100 amps through the wire given the size and distance.
At this point I had to start planning ahead. I would need to run conduit from the corner box to where the service would enter the workshop. I dug a trench from the house to the workshop digging below where the retaining wall footings would be.
Once I had the conduit buried, I then made an informed decision. I can do basic household and shop wiring but running service and hooking it up correctly was right on the edge of my lane. At that point, I called a local electrician. I would have them decide what amp breaker to install in the house panel and they would have the correct gauge wire for connecting the corner box to the workshop. I had already purchased a sub-panel for the workshop so I thought they might as well do while they are there. That way when they left, everything would be done and working.



The guys were here about three hours-money well spent. Now it was my turn. I had sketched up some plans, trying to be efficient with the conduit and wire. Especially the wire. I knew prices had gone up over the last four years but copper wire has doubled in price. I wanted to avoid waste where I could.



As the things progressed, some of the locations and descriptions would changed but these drawings were invaluable.



I also wired the shed for at least light. It is insulated but I won’t be storing anything in it that needs protected from the cold.


The shed had been wired previously and had numerous outlets in the finished and insulated walls but I had no idea if the wiring was corroded or had been gnawed on by varmints so I capped the outlets and ran my own. I only needed a couple of outlets for power, battery chargers and lights.


